2022 Air Canada Parking Lot Phase 2
Value
$1.2 million
Engineer
McElhanney

Client/Owner

YVRAA

Project Description

Fish salvage, ditch stripping, install of new and upgrade of existing storm utilities, including grade stabilization below and above the utilities and in the parking lot foundation. Excavation, removal of unsuitable materials to onsite proposed landscape area, combigrid, gravel placement and compaction, custom headwall, parking lot paving, curbstops, line marking, street lighting and fencing, hydro seeding and tree planting. Fire hydrant relocation and restraining.

Project Challenges

Working near the main landing runway for YVRAA it was important to have the appropriate permits in place and proper training for the crew. With great communication and co-operation with the YVR safety Authority everything went very well. Working next to the jet engine testing facility for the pacific northwest arose some concern that testing could be impacted, or send false signals however, with some vibration monitoring and great team work between the MTU team and the construction group there were no disruptions to either teams schedules. 

Responsibilites

• First Nations Archeological Chance Find Training.

• Construction Execution Plan.

• Safety Manager.

• Liaise with YVRAA Safety Team.

• Project Superintendent.

• Quality Control Plan Administrator.

• Schedule and Manage Supplies and Sub Contractors.

• Schedule and Manage Environmental Plan and Sub Contractor.

• Review and Confirm all Project Invoicing